This part of IEC 60953 establishes a Supplementary Standard for routine testing of steam turbines.
The rules given in this document follow the guidance given in IEC 60953‑0, but contain amendments and supplements regarding the analysis and supervision of relative performance by routine testing of steam turbine.
General principles for the preparation, performance evaluation, trends of performance parameters and the determination of the measurement uncertainty of periodic routine tests are given in this document.
This document is applicable to routine testing covering a wide range of accuracy on steam turbines of every type, rating and application, operating with superheated or saturated steam.
This document is not intended for application in acceptance tests of new units or retrofits and its application for such is strongly not recommended.
The purpose of this document is to provide simple and economic test procedures for conducting analysis and supervision of relative performance throughout the life of the turbine and turbine cycles.
The major purposes of routine testing are:
To provide guidance in scheduling maintenance outage on the basis of performance;
To detect or diagnose performance change in specific areas of the turbine or turbine cycle;
To provide results for unit economic dispatch curves;
To provide relative magnitudes of losses in steam turbine cycle before priorities can be established to correct deficiencies.
Specific simplified testing procedures are intended to minimize test instrumentation and personnel. Relative accuracy and wide uncertainty range rather than acceptance test level results are expected.
The repeatability of test results rather than test accuracy is emphasized in this document.
Routine test results can include as follows:
Performance of the turbine and turbine cycle
Thermal efficiency or heat rate;
Power output;
Steam rate;
Main steam flow capacity;
Nuclear: thermal load capacity of the steam turbine under defined conditions.
Component performance and trending parameters
Turbine stage flow factors;
Corrected turbine stage pressure;
Cycle isolation;
HP & IP turbine efficiency-expansion in superheated regions;
Heater, deaerator, condenser, boiler feedwater pump (BFP) and BFP turbine;
Gland Leakage flow from HP to IP (for HP/IP combined turbine).
Subclause 1.3 of IEC 60953‑0:2022 applies.
EN 60953-4 Ed.1.0
IEC 60953-4 Ed.1.0