1.1 General
RO.1 General
This Part 2-24 gives the requirements for planning, design and construction of overhead electrical lines with nominal voltages exceeding A.C. 1 kV operating at 50 Hz frequency.
The present Part 2-24 is not applicable for existing overhead electrical lines unless specifically required by Project Specification. The power installations of
overhead lines, that are in different stages of design or construction, can be finalised
in conformity with the standards in force at project beginning.
For the application of this standard for specific requirements relaring to modernization,
increasing safety and transport capacity of existing overhead lines, reference shall
be specified in the Project Specification. At the same time, the correlation between
relevant regulations and associated standards shall be established in the Project
Specifications.
The extension of existing electrical lines is considered as new overhead lines, except
the junction points that shall be detailed in the Project Specifications.